Span connection of Chu bridge (Luc Ngan)
The construction of Chu bridge started on November 15, 2020 with total investment of 75 billion VND (3.2 million USD) from the budget capital.
Construction of Chu bridge is speed up. |
According to Director of Tan Thinh Co.,Ltd Nguyen Van Quyen, the company mobilized all man power and materials to construct the project, even organized 3 working shifts per day on the construction site to realize the progress.
After connecting the bridge spans, the company will highly focus on constructing the remaining items of the bridge and two side paths so as to complete the whole project before May 30 (10 months ahead the set schedule) and put in operation on the lychee harvest season.
Chu bridge is built over Luc Nam river which is about 500 meter downstream of the current bridge. It is designed with 220m length, 4 piers, 2 abutments, 5 spans and 16 meter surface and applied the prestressed concrete technology.
It is among the meaningful projects to welcome the 46th anniversary of Reunification Day April 30 (1975 - 2021) and the election of deputies to 15th National Assembly and representatives to the People’s Council at all level in the tenure 2021 – 2026.