Bac Giang accelerates land clearance progress for Yen Lu industrial park
The investment policy for the Project was approved by Prime Minister in late 2021 with investor Capella Real Estate Joint Stock Company. It is implemented on total area of 377 hectares in Yen Lu commune with total investment of nearly 2.7 trillion VND (118 million USD), including over 403 billion VND from investor and mobilization capital.
![]() |
PPC Standing Vice Chairwoman Lam Thi Huong Thanh inspects Yen Lu industrial park infrastructure development project. |
The site work was divided into three phases. As schedule, 171 hectares of land are cleared on the first phase, 107 hectares on second phase and remaining area on the last one.
So far, the district has cleared nearly 138 out of 377 hectares and changed the land use purpose for 58.3 hectares. The investor has levelled 25 hectares and constructed internal road, waste water treatment station among others.
Concluding the supervision, the PPC Standing Vice Chairwoman Lam Thi Huong Thanh ordered Yen Dung district to take serious experience in managing and supervising the project execution and promptly have solutions to recover the shortcomings.
![]() |
PPC Standing Vice Chairwoman Lam Thi Huong Thanh concludes the supervision session. |
Local authority must focus more on planning work to restrict adjustment and prevent project distortion while directing competent agencies to accelerate the progress of land reclamation and compensation for land clearance in line with the approved plan.
The investor was urged to recover the proved limitations during project implementation and actively cooperate with Yen Dung district People’s Committee to handle the obstacles in site work, complete the formalities among others.