Speeding up schedule of Tay Yen Tu Spiritual Ecotourism Complex Project

Updated: 19:36, 03/08/2021
(BGO) – On August 2, Mai Son, Permanent Vice Chairman of the People’s Committee (PPC) in Bac Giang province, Head of the Steering Committee for implementing construction projects in at  Tay Yen Tu Spiritual Ecotourism Complex (Project) paid a field trip to review the project execution schedule in Son Dong district.  

The report showed that from January to August 2021, Son Dong district People’s Committee approved the compensation programme for site clearance in the 15th period with reclaimed area of 10.45ha, making up total area of reclaimed and compensated areas in the Project of 78.6ha (accounting for 80 percent of land for compensation); supported and verified the compensation programme for the site work in the 16th period...

{keywords}

PPC Vice Chairman Mai Son and delegates inspect the project construction site.

However, the project land clearance was delayed. Tay Yen Tu Service Joint Stock Company has not completed to adjust the Project Plan, causing impact on the schedule of land reclaimation and site work...

Concluding the inspection, PPC Vice Chairman Mai Son pressed that it was the key project in the province so the relevant sectors, localities, agencies and businesses must highly focus on speeding up the execution progress and strive to complete the site work for all projects within the third quarter in 2021.

{keywords}

PPC Vice Chairman Mai Son inspects the project implementation schedule.

Tay Yen Tu Service JSC should promptly complete document to adjust the Project Plan then submit to authority for approval before August 10; rapidly compensate for the cases suffering the loss on agriculture production due to project’s levelling work; pay for the amount to support early land handing over under the programmes of the 15th period.

The Project was devided into 3 stages, starting from 2014 and completing by 2025 (plan). After 7 year implementation, the items in first stage were basically completed and operated from February 2019. In the investment approval, total area of land for Project implementation covers more than 136 ha with reclaimed area of nearly 114 ha.

Cong Doanh

Bac Giang attracts 34 investment projects in 7 months
(BGO) – Bac Giang province attracted total investment of about 30.6 million USD in July 2021, accounting for 13.2 percent and 775.94 million USD in seven months, making up 87 percent comparing to the figure at the same period last year.
Bac Giang speeds up implementation of public investment projects
(BGO) - In the first half of this year, a series of works and projects using public investment capital in Bac Giang province were affected by the pandemic, even many of them were halted. To complete the disbursement plan for the whole year, these days, on construction sites, the working atmosphere is urgent with a determination to overcome difficulties.
Project launched to connect benefactors and needy people
The VNG Corporation on July 16 launched the ‘Sai Gon Bao Dung’ (Magnanimous Sai Gon) project, a technology platform that helps charity groups in Ho Chi Minh City and the whole country connect with needy people who are facing great difficulties due to Covid-19 pandemic.
Project launched to sort out outstanding tourism firms and service providers
The Vietnam National Administration of Tourism (VNAT) recently launched the ‘Vietnam Tourism Yellow Pages’ project on the occasion of the 61st founding anniversary of the country’s hospitality sector (1960-2021).
“Vietnamese Culture Bookcase” project launched
Chibooks and Literature Publishing House and Labour Publishing House have just announced the “Vietnamese Culture Bookcase” project with works written on the cultural characteristics of each locality in Vietnam.
Shares:
icon-zalo
speeding-up-schedule-of-tay-yen-tu-spiritual-ecotourism-complex-project.bbg

Reader's comments (0)

Your comment...