Bac Giang mobilizes resources to clear plane for industrial development
Several difficulties in site work
To accelerate the progress for investment construction and trading project in the infrastructure of Yen Lu industrial park (Yen Lu IP project) in Yen Dung district, Chairman of the provincial People’s Committee (PPC) Le Anh Duong on August 2 chaired a working session about this project implementation.
![]() |
PPC Chairman Le Anh Duong concludes the meeting. |
So far, Yen Dung district has made land reclamation plan and announced the first reclamation period of 173.47ha. However, the project execution is much delayed comparing to the prepared detailed plan.
Yen Lu IP project has huge reclamation area, causing big impacts on many aspects of life. The limitation in land handing over, leasing, issuing of land use certificate in previous years led to difficulties in identifying the origin of land use, reclamation area, support for land clearance among others.
At the same day, PPC Vice Chairman Phan The Tuan inspected the schedule of investment and construction project in the infrastructure of Tan Hung IP and investment and construction project in technical infrastructure of Huong Son industrial cluster in Lang Giang district (Huong Son IC project).
The site work encounters a lot of challenges due to complicated origin of land use. On the occasion, the investor to Tan Hung IP proposed Lang Giang district to urge local households to collect crops on cleared area and prevent any conflict while suggesting PPC to speed up construction progress of intersection point to Bac Giang – Lang Son Expressway to facilitate the investment attraction…
Regarding Huong Son IC project, the investors recommended to definitely handle the overlapped land in the section of frontage road under the expressway and IC projects so as to meet condition for handing the land for enterprise.
Absolutely handling obstacles
The infrastructure investment projects in the industrial parks and clusters have important role in the socio-economic development in the province in general and districts in particular.
![]() |
PPC Vice Chairman Phan The Tuan inspects the investment progress in Tan Hung IP infrastructure. |
PPC Chairman Le Anh Duong affirmed Yen Lu IP project as the key project in the province and district so successful implementation will lead to long term benefit. For such meaning, Yen Dung district and infrastructure investor were urged to tighten cooperation in project execution in upcoming time.
Yen Dung district should launch action period in two months to conduct site work at Yen Lu IP while the investor must urgently complete and start construction of waste water treatment station within October. All parties strive to build green, clean and beautiful Yen Lu IP.
The district needed to speed up construction progress of the road linking to Viet Yen district and apartment for workers. The PPC Chairman assigned PPC Vice Chairman Phan The Tuan to direct and review the execution progress of Yen Lu IP monthly while the district will implement weekly supervision.
Regarding the land clearance, the local authority and investors must finalize about the reclamation method to prevent the complaint. Yen Dung district was ordered to pay more attention to planning of communal welfare facilities, evaluate the affect of land reclamation to local people toward effective settlement.
The provincial leader requested the district People’s Committee to make detail plan of project execution then report to him before August 20.
For Tan Hung IP and Huong Son IC projects in Lang Giang district, PPC Vice Chairman highly spoke of the effort and creative method of local party and authority in implement land clearance at the IP and IC.
In the upcoming time, the district needed to focus more on the site work; quickly complete the IP infrastructure to attract sub-investors and further handle complaint; finalize the detail planning adjustment with unchanged exist road inside Tan Hung IP; hand over land for second time in August.
The provincial IP Management Board was requested to support investors in completing document to merge Tan Hung IC into Tan Hung IP in this August.
Meanwhile, PPC Vice Chairman ordered the district to focus on land clearance for the remaining area in Huong Son IC. The investor must accelerate to build waste water treatment for early operation.