Bac Giang strives to complete site work at extended Quang Chau IP before June 30

Updated: 16:05, 11/04/2023
(BGO) – On April 10, Vice Chairman of Bac Giang provincial People’s Committee (PPC) Phan The Tuan chaired a meeting about the project implementation of extended Quang Chau industrial park (Project).

Total extended area for the IP hits 90 hectares in Dong Tien and Quang Bieu villages of Quang Chau commune. As of April 7, 2023 the district reclaimed and compensated for 57.7 hectares of land.

{keywords}

At the meeting.

The PPC issued decision to change the purpose on December 22, 2022 and allowed SBG Company to lease the area and execute Project on 51.9 hectares (first phase, extension). Meanwhile, local authority continues clearing the remaining 5.8 hectares for purpose change as regulation.

The district basically compensated for the land clearance on the remaining 33.8 hectares and proceeded next formalities for reclaiming and handing over the land to the investor.

Concluding the event, PPC Vice Chairman Phan The Tuan affirmed early completion of the site work for the Project was very crucial to attract sub-investors. He urged Viet Yen district to further communicate and persuade land owners so as to create high consensus and complete the site work for the whole area before June 30.

{keywords}

PPC Vice Chairman Phan The Tuan directs the meeting.

Local authority was ordered to hand over available plane as well as the area with completed land clearance on time to the investor. The district must issue announcement of reclamation on tree area and N3 intersection in Quang Chau industrial park soon then complete document and submit to the authority for approval.

SGB must ensure expense for payment and strictly cooperate with Viet Yen district People’s Committee during the land clearance. The company was requested to fulfil document and procedures about construction, fire – fighting to complete approval for the Project Detail Planning with 1/500 ratio before April 30.

The provincial leader directed relevant departments and sectors to base on function and task to actively handle the issues in charge, ensure to accelerate the site work and project execution so as to effectively lure more sub-investor to extended Quang Chau IP.

The Dai
Bac Giang accelerates progress of traffic and social housing projects
(BGO) – Chairman of Bac Giang provincial People’s Committee (PPC) Le Anh Duong on March 30 inspected the implementation of social housing project for worker in new urban area of Nenh town in Viet Yen district and interchange project of Voi town (Lang Giang district) with Bac Giang – Lang Son expressway.
Phon Xuong town smoothly executes project by good mass mobilization
(BGO) – The Party Committee in Phon Xuong town, Yen The district of Bac Giang province has effectively conducted mass mobilization movement, helping solve many bottleneck issues in site work and facilitate the implementation of socio-economic development projects in the district.
EU-funded project promotes sustainable clam, bamboo value chain in Vietnam
The sustainable clam and bamboo value chain development in Vietnam (SCBV) project, funded by the European Union (EU) and implemented by Oxfam Vietnam in collaboration with Vietnamese partners, has benefited a large number of rural residents and stabilised these production areas in Vietnam, heard a conference in Vinh city of Nghe An province on March 23 to review the project.
Bac Giang accelerates progress of basic construction projects
(BGO) – On March 14, Vice Chairman of the Bac Giang provincial People’s Committee (PPC) Le O Pich chaired a meeting to judge the investment and construction in 2022 and work out main tasks and solutions in 2023.
470 billion VND invested to 5 new projects
(BGO) – This year, Bac Giang province mobilized 470 billion VND (nearly 20 million USD) from public investment capital to commence 5 new projects of school, medical and inter-organization buildings.
Shares:
icon-zalo
bac-giang-strives-to-complete-site-work-at-extended-quang-chau-ip-before-june-30.bbg

Reader's comments (0)

Your comment...