Bac Giang-Lang Son expressway to open 3 months ahead of schedule

Updated: 19:00, 25/08/2019
The expressway connecting Bac Giang Province with the China border will open to traffic in September, three months earlier than expected.

Works on the VND12 trillion ($526 million) expressway is 90 percent complete, said Nguyen Quang Vinh, head of the management board of Bac Giang – Lang Son BOT JSC which is executing the build-operate-transfer (BOT) project.

{keywords}

The Bac Giang – Lang Son expressway is part of the 143 km Hanoi – Lang Son expressway.

"Minimum works required to open the expressway to traffic will be completed before September 30, three months ahead of schedule," Vinh said, but did not comment on when the project will be finished in its entirety. The project was originally scheduled to complete this December.

Currently, works on the foundation, road surface, and drainage systems of some sections are still ongoing, but operators will focus on finishing laying asphalt on the whole expressway by September 15, Vinh added.

The expressway connecting Bac Giang, a province to the north-east of Hanoi, with the northern province of Lang Son is expected to enhance trade between Vietnam and China.

The four-lane expressway is 64 kilometers long, 25 meters wide, has a designed speed of 100 km per hour, and runs parallel to a strip on the existing National Highway 1A (Vietnam’s 2,300 km transnational highway) which connects the two provinces.

This route will collect toll for 17 years, 2020-2037.

Work on the expressway started in October 2015 and was scheduled for completion last year. However, the Ministry of Transport had to select a new investor for the project after the original one ran out of capital.

The Bac Giang – Lang Son expressway is part of the 143 km Hanoi – Lang Son expressway, connecting the capital with the Huu Nghi International Border Gate in Lang Son Province.

North-South Expressway a top priority for government in 2019
Eleven components of the North-South Expressway are among the top priority this year, the government has said.
Da Nang – Quang Ngai Expressway fully put into use
The entire Da Nang – Quang Ngai Expressway was open to traffic on September 2, helping to cut down the distance among economic hubs of the central key economic region.
Ha Long-Hai Phong expressway opens to traffic
The Ha Long-Hai Phong Expressway was open to traffic at a ceremony on September 1 which saw the attendance of Prime Minister Nguyen Xuan Phuc.
New $556m Ha Long expressway to open in early September
A new expressway connecting the world-famous Ha Long Bay with the Hanoi-Hai Phong Expressway is almost finished.
Efforts made to complete land clearance for Bac Giang – Lang Son expressway ahead of Tet
(BGO) – Vice Permanent Chairman of the Bac Giang province People's Committee Lai Thanh Son has chaired a meeting to review the progress of site clearance for the Bac Giang - Lang Son expressway project. Leaders of several provincial departments and sectors and the People's Committees of Lang Giang District and Bac Giang City attended the event.

Source: VnExpress